SHILLONG, APR 4: Cabinet Minister and South Shillong legislator Sanbor Shullai on Saturday emphasized the significance of the Shillong-Dawki road project, stating that it is has the potential to become a crucial component of the pan-Asia integrated intermodal transport system.
“The project road is part of Asian Highway (AH) and has the potential to become an important building block for pan-Asia integrated intermodal transport system,” Shullai said while addressing at the inauguration of a link road on Saturday.
“Once the project road is completed, there will be improved connectivity with Bangladesh and contribute to the growth in international trade.”
The project is expected to boost tourism in the region by improving access to popular destinations like Shillong peak, Elephant Falls, Dawki, Cherrapunji, and Mawlynnong, Asia’s cleanest village.
“It will improve access to tourist destinations, promoting tourism in the region,” Shullai added.
The 71-km Shillong-Dawki corridor is being developed with a 2-lane Paved Shoulder configuration, with 4-laning provisions in certain stretches. The total project cost is ₹2,171 crore, including land acquisition and other expenses.The project is divided into 5 packages, with 4 out of 5 projects sanctioned in 2020.
However, the projects faced delays due to land unavailability and public utility issues. “With constant effort, the hindrances were resolved, and the 4 projects were re-started between October 2022 to May 2023,” Shullai said.
The project timeline varies, with Package 1 (Rilbong to Mylliem Marbaniang) nearing completion (90% progress), while Package 5 (Umsyiem to Tamabil), including the iconic Dawki Bridge, is expected to be completed by 2027.
Package 3 (Pynursla Bypass) is set to start in April 2026 and finish by 2028.
By Our Reporter
Shillong-Dawki road to enhance tourism and trade with Bangladesh